Application deadlines for filming during the SUMMER SEASON 2026


Due to the increasing number of events, the growing workload of the authorities, and the reduced capacity of the approving committee, the submission deadlines have been adjusted.
 

What does this mean for you?

  • Plan ahead: We recommend adjusting your scheduling and taking the current deadlines into account. Please ensure your application is submitted on time to avoid delays.
  • Paperwork: Make sure all required documents and information are complete and correctly attached to your application. This will help us process your request quickly and efficiently.
    For more general information: Film Commission | Visit Brussels

 

Deadlines:

THE SUMMER PERIOD APPLIES UNTIL THE END OF SEPTEMBER.

Please take the submission deadlines into account. Requests submitted after the deadline may be refused.
 

Anderlecht (1070):
45 working days + 5 working days for processing your application
No council meetings between 15/07 and 15/08.

Auderghem (1160):
30 working days + 5 working days for processing your application
No council meetings between 15 July and 15 August. 

Berchem-Sainte-Agathe (1082):
30 working days + 5 working days for processing your application
Please note: if your request involves a street closure, requires the intervention of the SIAMU, or impacts a regional road, the processing time is 45 working days, plus an additional 5 working days for administrative handling of your application.

Bruxelles-Ville / Laeken / Neder-Over-Heembeek / Haren (1000/1020/1120):
35 working days + 5 working days for processing your application
Depending on your request, the film commission will assess the processing of the dossier.
Due to the large number of planned events in Brussels 1000, certain areas are subject to filming restrictions.
We kindly ask you to contact us before submitting a request or if you have any questions.

Etterbeek (1040):
21 working days + 5 working days for processing your application
No council meetings between 15 July and 15 August. 

Evere (1140):
30 working days + 5 working days for processing your application

Forest (1190):
20 working days + 5 working days for processing your application
All applications related to filming before 15/09/26 must be submitted no later than 30 June.

Ganshoren (1083):
30 working days + 5 working days for processing your application
No council meetings between 17/07 and 14/08. Last possible application on 25/06.

Ixelles (1050):
15 working days + 5 working days for processing your application

Jette (1090):
20 working days + 5 working days for processing your application

Koekelberg (1081):
30 working days + 5 working days for processing your application

Molenbeek-Saint-Jean (1080):
15 working days + 5 working days for processing your application
No council meetings between 15/07 and 15/08. Last possible application on 25/06.

Saint-Gilles (1060) :
10 working days + 5 working days for processing your application
Please note: no council meetings between mid-July and 20/08 (approximate dates). This means that any request concerning communal buildings cannot be approved during this period.

Saint-Josse-ten-Noode (1210):
20 working days + 5 working days for processing your application
No council meetings between 15/07 and 15/08. Last possible application on 25/06.
Due to the high police workload in the area, please allow for a longer processing time.

Schaerbeek (1030):
21 working days + 5 working days for processing your application
Due to the high police workload in the area, please allow for a longer processing time.

Uccle (1180):
15 working days + 5 working days for processing your application
Please note:

  • Any urgent procedure or urgent extension request for an initial authorisation must be submitted no later than 7 calendar days before the start of the activity, plus an additional 5 working days for administrative processing.
  • A 25% surcharge on the total fee applicable to the filming or photo shoot will apply, unless the activity falls under an exempt category.
  • However, please note that submitting a request under this procedure does not guarantee that it will be processed. Each request will be assessed based on the current volume of files and the processing capacity available at the time of submission.

Watermael-Boitsfort (1170):
25 working days + 5 working days for processing your application

Woluwe-Saint-Lambert (1200):
15 working days + 5 working days for processing your application

Woluwe-Saint-Pierre (1150):
10 working days + 5 working days for processing your application

Contact and support

We understand that this change requires some adjustment and we are here to support you.
For any questions or additional information, please contact us by email at tournage@visit.brussels or by phone at +32 2 289 60 82.

Please note that our team will be operating at reduced capacity during the month of July.
As a result, some services may take a little longer than usual. We will do our utmost to process your requests as quickly as possible.